CyrusOne Data Center

Location: San Antonio, Texas
Client: CyrusOne

Building II started as site retaining walls only for two new building additions adjacent to the current site and then evolved into the entire Building 2 facility including data center ft up complete in 7.5 months. This tilt-wall and precast structure houses a single tenant (Fortune 100 client) with 18 MW of critical load, totaling 188,617 SF. With a 7.5 month schedule, this ground-up project was completed on time from start to a fully commissioned data center with 4 months of around-the-clock construction. To reduce noise to an adjacent residential neighborhood and two separate utility yards, 30’ tall sound barrier walls were installed on the entire west side of the project site. These walls consisted of poured-in-place concrete, tilt panels and precast at various areas of the building  to remain within the sound ordinance levels.